Step 6: The Aquadam® has been installed across pipes and stream from
bank to bank, making a 99% seal. Some seepage will occur, especially
on big cobble like that shown in the picture to the right. Water is
still being pumped into the Aquadam® to force it to grow to its
optimal height, which in this case is three feet.
Step 7: The unused portion of Aquadam® left on the roll is tied off to
the bank using a rope, keeping it from falling off the bank and unrolling.
The Aquadam® is inflated to its optimal height. The pumping time for phase
1 is 33 minutes.