Installation Example
Eagle River
Vail, CO(2000)
Page 4 of 6
The 4' AquaDam® has been fitted into the attachment collar. Fill hoses have been inserted into the fill tubes. The 4' high AquaDam® is now ready to receive water.  
Vail, CO
Four workers are standing behind the 4' AquaDam®, using their legs to keep it from unrolling. Two workers on ropes are needed in case the AquaDam® needs to stop unrolling. It can be tied off until you are ready to resume work.
Vail, CO
The 4' high AquaDam® has been installed and connected to the end of the first 6' x 100' AquaDam®. The Eagle River flow has now been forced to the far bank and the work area is isolated from the clean, flowing water. We are now ready to install another 4' x 50' AquaDam®.
Vail, CO
The 4' x 50' AquaDam® installation has been completed. It is attached to the 4' x 100' AquaDam®, which in turn is attached to the 6.5' x 100' AquaDam®. The 6.5' AquaDam® starts open-ended on the bank.
Vail, CO
We then connected a 3' x 100' AquaDam® to the end of a 4' AquaDam®. This closed off the downstream end of the work site.
Vail, CO