| Installation of the AquaDams® has been completed. The Eagle River is now diverted and water is flowing through the existing high-water overflow channel. Notice the foot traffic on top of the AquaDam®. |
![]()
|
| Diverted river flow was pushed down to only a 20' wide channel along the north side of the river. The south side of the river (80%) is now an isolated work area. Notice how clean the water is. A large number of boulders had to be removed to achieve a workable seal for dewatering. |
![]()
|
| This shows the end result of the installation of the AquaDams®. Installation time was 14 hours. The excavation process has not yet been started, however. |
![]()
|