Connected a 3' high by 100' long AquaDam® to the end of a 4' high AquaDam®. This will close off the  downstream end of the work site.

Water is diverted to existing high-flow channels on the river bar.  Work area has been isolated for later dewatering. Remaining water is trapped and needs to be pumped out in order for the work area to be dewatered. The work area will be excavated to an area  6' below the riverbed, before intake pipe gallery laterals can be installed.  A large portion of the work area will be used to store excavated material.