Stream Diversion
Phase Two
Antelope Creek
Lincoln, CA (2000)
Page 6 of 7
Keep repeating the process until the AquaDam® is unrolled completely across the stream. A minimum of 3 workers are required for a project of this small size: two to hold the AquaDam® and maintain a head inside it, and one to run the pumps. 
Lincoln, CA
Don't get in a hurry! The capacity of your pumps determines how long the installation will take, not how fast four people can unroll the AquaDam®.
Lincoln, CA
Installation time for the downstream AquaDam® was approximately 15 minutes from the time the pumps started filling. The work site is now ready to be dewatered. The water is pumped over the top of the AquaDam®.
Lincoln, CA