Stream Diversion
Phase One
Antelope Creek
Lincoln, CA (2000)
Page 2 of 7
Before diversion begins, a proper site must be selected. Fill material excavated earlier from the canal made perfect banks to start the AquaDams® on.
Lincoln, CA
The contractor was required to line the sides and bottom of the diversion channel to prevent erosion. This is the upstream AquaDam® which is 4' x 50'.   
Lincoln, CA
The protective cover and ropes are removed. The open end is placed higher up the bank than the estimated height of the AquaDam®. Workers need to be careful not to let the current carry the AquaDam® downstream. 