Figure 6: SHORING-UP
CROSS SECTION 
Figure6. A cross section showing the placement of earthen fill material to shore up
an AquaDam® that shows signs of lateral movement.
Certain applications require that two or more AquaDam® sections be linked or coupled together to form a longer continuous water-filled cofferdam or barrier. The following procedure illustrates how this is accomplished (the procedure assumes that the AquaDams® are being joined in a straight line end to end). All standard closed-ended AquaDams® come with a coupling collar on the closed end. The other end has the fill tubes, and has been designed to fit snugly into the coupling collar.
| Step 1: Before a second AquaDam® can be attached, step one is to install an AquaDam® with a coupling collar. The other end of the coupling collar is already tightly secured around the end of the previously installed AquaDam® that has already been inflated with water. |
|
| Step 2: Position the second AquaDam® directly behind and in-line with the filled AquaDam® and unroll about 10 feet of the new section, plus the length of the fill tubes (see Figure 7a). |
|
|
Intro |
Concept |
Applications |
Site Criteria |
Installation |
Maintenance |
Removal |
Safety |
Specs |
Pages: 1 2
3 4 5
6 7 8
9 10
11 12 13
14 15
16 17
18 19
20 21
22