Boat Ramp Replacement Little Creek Naval Base, Norfolk, VA (2001)
Page 4 of 21
Another view of the dewatered work area.
The excavator is placing fill material (dug out of the bay bottom) next to the
AquaDam® to help support it. The outside edge of the AquaDam® is actually 1-2'
lower than the area where the workmen are standing.
The workers next to the red part of the AquaDam® are standing on a 2' high
berm left over from the sheet pile cofferdam.
The workers are digging a sump hole so that the 6" suction hose will work properly.