Dewatering Anabranch River Construction of Concrete Culvert Footings New South Wales, Australia (2003)
Page 1 of 1
Two ponds needed to be connected for drainage. The job called for the
installation of two culverts in the berm separating the two ponds. A
concrete footing also had to be constructed to prevent scouring and erosion.
One 4' high x 100' long AquaDam® was placed on the north side of the berm.
Another 4' high AquaDam® was placed on the other side of the berm to
isolate the work area. The work area was then dewatered using portable pumps.
The berm had to be excavated out so that the culverts could be installed.
The contract called for a dry work area because concrete footings needed to
be poured. Water quality prohibited the use of earthen fill material to form
the cofferdam.
Once the work area was isolated, the water was pumped out, and the concrete
footings were poured. Once the concrete was finished, the AquaDams® were
removed with no detrimental impact to the surrounding aquatic life.